- Apart from daily visual inspections, Fresh Gland Packing is checked monthly. If leakage is found from gland, same is required to be tightened.
- Coupling alignment and integrity is to be checked monthly .
- Tightness of foundation and "hold down bolts" is to be checked every 6 months.
- Both DE and NDE side bearing greasing and coupling greasing is to be done in 6 months.
- Shaft, sleeve, short sleeve, neck ring and impeller are to be checked after openeing top cover of pump every year.
- Every year running clearance of impeller is to be checked.
- Non -Return-Valve is to be checked every 6 months.
- Packing and greasing of sluice valve is to be carried out every 6 months.
33 KV power supply is taken at MSS from DVC and fed to main workshop , TM, Steel Foundary, Township and Water Supply through one 12 MVA transformer, three 10 MVA transformer and one 6 MVA transformer.PF is maintained at 0.94. There are 42 outdoor type and 21 indoor type ( 11/0.4) sub stations.One 3.3 KV Sidhabari substation serves pump house. यह ब्लॉग चित्तरंजन के पावर सप्लाई सिस्टम और तकनीकी बारीकियों के बारे में चर्चा का माध्यम है.